Our client at Forbes Place professional services required the installation of 2 new dual outlet 7KW charging hubs for their shared car parking space at Forbes place in Paisley.
As there was no capacity on site for additional load following the site survey, Powertek were required to install a new feeder pillar to house a new LV supply from the DNO networks and the control equipment for the EV charging hubs.
All design, civils installation works, electrical Installation, cable install and final closing joints were carried out by our own in house resource. Powertek fully managed the DNO connection for the customer including arranging installation of meter and final commissioning of the charging units
Our client was also able to recover £2000 from the governments workplace charging scheme grant which was also managed by Powertek.
On completion of electrical install Powertek carried out the full resurfacing of the customers carpark, line and bay markings and installation of signage and lighting